Can a P6 Global Change be designed to be an activity counter?
I
I'm designing a new layout that I want to display only the first three activities under a WBS value. I'm looking to use a global change to flag the first three activities and a layout filter to display those three activities.
A manager wants to see a layout that displays the first three milestones for each project in a multiple project layout. I can set something up manually, but I am currently trying to get a GC to count the activities and stop when it reaches 3 (or continue for all activities under a WBS value, either way). Then the layout filter will display the activities that have a value of 1, 2, or 3. I'm using the activity counter field to help with the GC, but it puts the same value for each activity.