Hi Folks,

We are trying to work on scenario of PO integration with Projects.

We have created the Project which is approved,created the budget in Project Management and baseline the budget.

Created a PO with Project and when we do the Funds check,we could see the exception as "There is no baselined budget for this project".

Could anyone suggest on this.

Baseline budget for the project screenshot.

PO Funds check error

Regards

Raj