Layout using 'Rolling Dates' ignores finish date when levelling
Hello All,
I usually 'schedule' my programmes but my current programme I am 'levelling' the resources.
I usually use a layout with rolling dates for the start and finish e.g. START: PS-4w and PF+6w for the finish.
However, using the rolling finish isn't working when I have levelled activities which go beyond the 'scheduled' finish date.
It seems the layout is using the latest scheduled finish date to define the layout finish rather than the latest levelled finish date.
Steps to reproduce inc screen shots in the attachment:
- Create a layout with rolling start and finish dates - e.g.: