Is there a way to set the Approver Due Date on a negotiation?
The Due Date specified in the Bechtel EBS Workflow email is when the action within the notification should be completed by. There are currently no controls which allow the requester to manually enter a specific date for the Approver to approve the negotiation by, however certain Control settings have an effect on when the Due Date will be.
1. If the Preview Date and Open Date are set to “Immediately”, and a Close Date is assigned: the approval Due Date will be halfway between when the negotiation is submitted for approval and the Close Date.
2. If the Preview Date is set to “Immediately”, the Open Date is set to a specific date, and a Close Date is assigned: the approval Due Date will be about 30 minutes before the Open Date.