PRP Demand Explosion
Hi all
I'm not sure about a specific situation related to the PRP Demand Explosion.
if i create a Project configured WO from MRP (Demand Project related)( WO number 1 Item A) .
The item for which i ve created the WO has no BOM(Item A has no BOM).
Than i add a child WO(number 2) to the one just created(using the functionality of P31P001 that allows to create sub layer to a WO manually): this new WO produces an ITEM with a BOM(Item B with component C and D).
the only way to create a project demand for C and D is to put B in the part list of the WO 1(or create a BOM for A that contains