Order Preparation Days Basic and Advanced Preference Profiles / Delivery Date Basic and Advanced
Usually, when the manufacturing enterprises in the planning of MPS, expect it to order preparation days to the customer commitment, the date of the order (requested date <DRQJ> ) and make ready for days as Scheduled Pick Date PDDJ (the date usually demand is greater than the number of days the Planning Fence MTF1), in this way, planner has a enough MPS plan date plan for the future.
However, the order preparation days in the current system can only be defined as a positive number, so that the promised delivery date (RSDJ) must be manually modified to a future date to calculate the Scheduled Pick Date (PDDJ) and Promised Ship Date (PPDJ) , which is a disaster for the business personnel who frequent order entry!