Cancelling/Suspending PM Schedules
Hi,
My customer has a need to cancel or suspend some PM Schedules to stop Maintenance WMs being created.
I have tried various methods of updating the PM status to 98 (Cancelled) or a new status for Suspended including:
P13075 - Global PM Update
R12807 - PM Schedule Generation - I tried to select the PM schedule and update to status 98 with no WO created by using a past due date.
P12071 - PM Backlog
Sadly, none of these methods worked. The only option I can think of is to delete the PM Schedules from P13075 - Global PM Update and Form Exit to Delete or to exclude the equipment items from the regular R12807 Data Selection (the latter gives the option of adding back in again at a future point without needing to recreate the PM Schedule)