"Update progress" and "Update Baseline" functions. "Planned Dates" take precedence to Calculated dat
When using either the "Update Baseline" or "Update Progress" functions for activities that have and "Actual Start" date the software updates the finish date of the activity to the "Planned Finish" date ignoring any earliest finish date. I do not understand why the software should use "Planned Finish" dates. Can anyone shed light on this?