Sub-assembly Job created by Autocreate final Assembly Order does not have Correct Dates

edited Jun 13, 2019 9:21AM in Discrete Manufacturing - EBS (MOSC) 6 commentsAnswered

We are Creating Job for ATO Assembly from Sales order, When AutoCreate Final Assembly Orders runs it also create the Sub-assembly Jobs. However the Child Job Completion date/time is after the Material Requirement time for those sub-assembly on Parent Job.

Sub assembly items have supply type as Operation Pull.

We are using ATP plan for scheduling. Attached documents with some screen shots.

Regards,