Mutliple planned orders on same day for same item
Hello experts,
We are observing multiple planned orders created for same item-supplier-org on the same date.
The item have FDS as 5 days, PTF as 5 days. The planned orders are way beyond the PTF date, as plan run date is of 18-Apr here.
Also, there is single Supplier source against these items. Plan is not checked for Lot for Lot option.
The profiles are having values as :
MSC: Split Planned Order to perform safety stock pegging =No
MSC: Split Planned Orders for Scheduling Flexibility=Yes
MSO: Split Planned Orders for Assigned Units=Yes
Could you please advise to identify and fix the issue. We expect there should be single planned order on the same day.