Hi We are using 9.2.
Can you help me understand the relationship of the freeze fence on the item branch and the Planning Weeks processing option on the R3482?
Our user has a item with long freeze fence, 18 months. We are simply ordering based on safety stock, no forecast. He runs MRP but is not getting a message to purchase this item.
I tried to enter a Planning Week horizon of 52 weeks but all messages are cleared and this error is on the PDF Error Message: Past Due + Days + Weeks + Months should not be Greater than 54.
I read the document 625968.1 that