Schedule Management in Unifier
Dear all!
I am working with Unifier connected to a P6 environment, I am still learning how the schedule capabilities for Unifier works, but I have some questions that maybe you could help with!
The first thing I am wondering is why there is an Activity Sheet and a Schedule Sheet, where the information is different... I have seen that the information coming from P6 is stored in the Activity sheet, where I cannot edit it, but it´s not available in the schedule sheet where I would be able to work with it. Is it supposed to work like this? I am not sure if I am doing it OK, but this is how our GSE environment is configured.