Why are sales orders that exceed the Planning Fence days and are smaller than the forecast consider
Item 400 is a manufacturing part.
1.The F4102 MRP is set as follows:
Planning Fence Rule: C- Within the planning fence :Customer Demand / Out of planning fence:Greater of Fcst or Cust Demand
Planning Fence :5
2.Sales order:
3.Forecast:
4.Calendar:
5.R3482 Process Opration:
UBE运行时间:2019.5.24
6.P4021:
Both June 1 and June 2 are non-working days, Out of planning fence, and the forecast quantity of these two days is greater than the sales order quantity, but it seems that MRP use the recommendation message generated by the sales order quantity instead of the larger forecast quantity.
On June 8, also a non-working day, the normal logic-MRP generates the number of suggested messages using the forecast quantity.