Budgetary Control - query about Project and Task settings
Hi,
We are using R12.1.3.
I have a question about Project Budgets, and Budgetary Control.
Here's a screenshot of a Budget from a test system:
And going to Tools > Budgetary Controls, we see
The Control Level at Project level is Absolute...
However - I have noticed that if there is e.g. £50,000 Budget against e.g. Task 4, I can still raise a REQ for £50,000 against Task 1, even though it has no Budget against it.
Is that because there are Controls at Task level, which are set to None?
Thanks
Jim