Primavera Gateway Custom Adapter
Hi,
We are in phase of integrating Primavera P6 and IBM Maximo. Below are the details furnished. Anyone please suggest us to proceed further.....
SOURCE : IBM MAXIMO 7.5 Database Tables
TARGET : Primavera P6 18.8
MIDDLEWARE : Primavera Gateway 18.8 ( P6 Provider, Custom Provider and Gateway objects )
USE CASE :
--------------
We have to integrate all Work-Orders created in IBM Maximo we should send it to P6 and we need to get back schedule dates back from P6 to Maximo.
1. We want to fetch the work order details from Maximo database tables.
2. Create or Update project, WBS and activities in P6 based on Maximo Work-Orders.
3. We have to bring schedules dates from P6 and integrate to Maximo.