Say that a configured item has this setup in the org item

and the ATP-2 rule has infinite supply set to CUM MFG Lead Time...however there is nothing filled in for a CUM MFG Lead Time for the configured item yet all the components have their lead times properly filled in. What is the expected behavior either in OM or in an ATP Inquiry?

Thanks in advance