Model forecast and demand time fence in ascp

We forecast at the model. Say the model has a demand time fence of 100 days. Under the model is OC-1234 and the demand time fence is 20. Under the OC is PH-1079 and the demand time fence is 0. Under the PH is CU-4567 and the demand time fence is 40. 

Planned orders for model start 100 days out

Planned orders for oc-1234 start 20 days out

Planned orders for ph-4567 start today

Pegging to on hand and planned orders for cu-4567 start today

Our expectation is that we wouldn't see anything pegged to the forecast for close to the 100 days when the model forecast drops off.