PM Workorder does not create all operation sequences defined on the Maintenance Routing
Hi,
We have defined a maintenance routing with 2 operation sequences 10 and 20, with seq 10 having a resource and duration of 2 hrs and seq 20 having a resource and duration of 1 hr. We also defined the routing network with sequence 20 dependent on seq 10. When we implement the PM workorder from the maintenance workbench for this activity, the workorder gets created with only operation sequence 10 and duration as 2 hrs.
Why is the operation seq 20 not being added to the workorder? Are there any setups needed to get the seq 20 to show up in the workorder?
Please see below for the details of the maintenance routing and the workorder created.