Dear Srini and Arun,

We have an requirement for meter based Preventive Maintenance

Activities 500,1000,1500,2000

Usage per day 9 Hours

for example forecasting suggesting

500 HR service at 27-jun-2019 and

1000 Meter hour's at 10-Jul-2019  

1500 Meter hour's at 20-Jul-2019

2000 Meter Hour's at 30-jul-2019

in actual scenario for 500 meter service is supposed to be on 30-jun-2019 instead of 2-jun-2019 user wants to re-schedule the same at the same time other activities should as per meter reading's and if that needs to be re schedule that has to be by manual

How can we handle this

Regards,

Sai

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center