The scheduling of resources is not correct based on ATP results
HI Experts,
We have a scenario where while scheduling the SO for ATO item, we get SSD at a date for ex. on 15th Aug, due to resource constraints for one of the resource named as 'ASYP'.
This is because the ASYP resource is not having cum capacity till 14th Aug and its overloaded already.
After scheduling the sales order line and progressing further, the work order gets created automatically by auto-create final assembly program.
But after the operation on this resource ASYP, we have few more operations which need at-least 2-3 days for completion of WIP job.
But, when the work order is created it can be seen that this work order has completion date of 15-Aug and from there it is scheduled backward and the operation for this resource ASYP is actually scheduled on 13-Aug. But since on 13-Aug, the resource ASYP is overloaded, it should actually shcedule the operation on it on or after 15-aug.