Question about updating Project Performance Reporting Data on Self Service Pages
Hi,
We are using R12.1.3.
In Self Service Projects, we have a "My Projects" page which is a bit like the PSI screen in Core Applications and contains this type of output:
We had an issue where the values were not updating correctly despite these jobs running regularly:
- PRC: Process Project Financial Data
- PRC: Refresh Project Summary Amounts
- PRC: Refresh Transaction Summary Amounts
- PRC: Update Project and Resource Base Summaries
- PRC: Update Project Performance Data
- PRC: Update Project Summary Amounts
In the end we fixed the issue by using this workaround:
- Set Profile option "PJI: Truncate PJI Summary Tables" to "yes" at the site level