Resources Not Assigned to Project Appear in P6 Leveling Log (P6 6.2, P6 15.1)
Two separate P6 projects for two different clients are seeing resources in the leveling log that are not assigned to the project during leveling.
Only selected project resources are being leveled (Not All). Only settings are 'Preserve Scheduled Early and Late Dates' and 'Level Resources Only Within Activity Total Float'.
I've tested in my standalone environments (P6 17.12, P6 18.8) while adding additional resources in the pool beyond those in the projects and cannot duplicate.
I also cannot find any related article or bug in My Oracle Support searches.
Has anyone else encountered this?