Does PA Funds Checking ignore some Expenditure Types?

edited Jul 25, 2019 12:19AM in Projects - EBS (MOSC) 1 commentAnswered ✓

Hi,

We're using R12.1.3.

We're having an issue where some Projects are being overspent.

For example - this Project has a €2.5m Budget against it:

With the 2.5m split across 3 Tasks:

Budgetary Control is set to the following on the Project:

The Project has 3 Expenditure Items against it.

They total 2,720,100.

However, only 2,500,000 Budget is against the Project.

The first 2 Expenditure Items were created via WebADI and sum to 2,475,100.

That should have left only 24,900 available to spend on the Project.

However - this was able to happen:

  • Raise a REQ for 245,000
  • Approve the REQ
  • REQ converted to a PO, and the PO was approved

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center