How To Change the Default Need-By Date in iProcurement

edited Jul 30, 2019 10:09AM in Procurement - EBS (MOSC) 5 commentsAnswered ✓

Hello,

We're trying to change the requisition default need-by date in iProcurement from 2 to 5.  We've changed the POR: Days Needed By profile from 2 to 5 and bounced Apache, but the requisitions continue to have a Need-By Date 2 days from the request date.

Could someone please advise if there are additional steps to be taken to change the default need-by date?

Thank you.

Debby