(F112) The transaction failed budgetary control at the project level - on PO Approval

edited Aug 14, 2019 5:06AM in Projects - EBS (MOSC) 2 commentsAnswered ✓

Hi,

We're using R12.1.3...

I have a Project with a €100k Budget against it:

There are €86,200 Actuals and €13,800 Commitments against the Project.

Initially a REQ was raised against the Project for €85,000.00, and that was converted to a PO.

The PO Value is also 85,000 but it has €86,200 matched against it. One of those invoices is on hold now with a QTY ORD Hold against it as expected, since Quantity billed exceeds quantity ordered.

The REQ value has been increased from €85k to €100k, and that has triggered a POREQCHA Change Request Workflow, which has updated the REQ value. The PO value is now

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center