R3483: Is there a maximum number of Branches & planning horizon working days allowed in any one plan
Hi,
Document 886502.1 references a limit on the number of branches and working days in the planning horizon "The planning horizon is also limited by a planning array size that needs to be balanced between the max number of branches and the count of work days for the entire planning horizon." see paragraph and document link below.
Does this mean the number of working days multiplied by the number of branches in any planning run(R3483) can not exceed 1200?
"
Planning Horizon Periods
Planning Horizon periods are set up processing option # 3: Planning Horizon Periods on the Horizon tab behind MRP Planning (R3482/R3483).