WIP Mass Load Program Completed with Warning
Hi All,
I am trying to copy an existing job to create a New Job by using interface program WIP Mass Load. But it is completed Warning with below error messages.
Error: Invalid value for Scheduling Method.
Possible causes:
1. You must enter start and completion dates to use manual scheduling.
2. The start date must be earlier than the completion date when using manual scheduling.
3. You cannot use lead time scheduling for nonstandard jobs without routing references.
0 out of 1 jobs were successfully loaded
Thanks in Advance.
Thanks
Ashok