PRC: Create and Distribute Burden Transactions - not picking up some Expenditure Items
Hi,
We are using R12.1.3.
We have an overnight Request Set called Overnight PA Request Set which consists of these jobs:
- PRC: Interface Supplier Costs
- PRC: Distribute Usage and Miscellaneous Costs
- PRC: Distribute Supplier Cost Adjustments
- PRC: Create and Distribute Burden Transactions
- PRC: Generate Draft Revenue for a Range of Projects
- PRC: Generate Revenue Accounting Events
- PRC: Generate Cost Accounting Events
- PRC: Create Accounting
- PRC: Update Project Summary Amounts
- PRC: Update Project and Resource Base Summaries
- PRC: Update Project Performance Data
- PRC: Summarize Unbilled Receivables/Unearned Revenue Balances Process
On 12th Sep 2019 that Request Set ran as follows:
Each day, we find a number of items are not included / picked up by