Releasing planned discrete jobs from ASCP - MRP
Hi everyone
I'm struggling with a problem which concerns releasing of planned orders for finished goods from ASCP. I created two plans:
MPS (Production plan) - planning of Finished Goods in weekly buckets with BOR - demand schedule for MRP plan / refresh 1x/week
MRP (Manufacturing plan) - Re-planning firmed planned orders from MPS with Routings, creating discrete jobs / refresh everyday
I would like to create discrete jobs from MRP plan, but when I do so, collect WIP data and refresh MRP, ASCP suggest another planned order release despite the discrete job was created (Planned order in the MPS plan does not get netted).