P6 EPPM R19 - Define project baseline for multiple projects and restore baseline
Hi,
In P6 Professional R6.2, was able to open multiple projects, add baseline to these (via Project/Maintain baseline) then assign these new baselines to individual project (via Project/Assign baseline).
Do not seem to be able to do this with P6 EPPM R19? Is there a way to do this?
Thanks.