Manufacturing Lead Time Calculation.
Hi,
We are not able to calculate Lead time % for one of the routing.
We checked below Points but still not able to calculate.
- Assembly Item should Make Item
- Primary routing only consider Lead Time % (Not Alternative Routing)
- Also tried with all the resources with Schedule option – Yes ( In Production for some of the resources are with schedule option – NO)
- All Resources are Active
We tried from both the way --- 1. Run the Request (Calculate Manufacturing Lead Times GUI) 2. From Tools Menu.
Every time request ended with error message - APP-BOM-20597: Lead time calculation for 18008213-003 failed
Please provide your thoughts.