Lease with 2 billing lines: Bill 1 line in advance and 1 line in arrears
We have the following use case:
We want to have 1 lease with the following lease details:
Lease class: Revenue
Lease commencement date: 01-JAN-2019
Lease termination date: 31-DEC-2019
Billing line 1. This billing line needs to be billed on the first of the month, so we have set it up as follows:
Frequency: Monthly
Start date: 01-JAN-2019
End date: 31-DEC-2019
Schedule day: 1
This will generate the first billing item on 01-JAN-2019.
Billing line 2 is about the same lease period and with a monthly frequency, but the billing schedule needs to be generated exactly 1 month in arrears, so the first billing item should be generated on 01-FEB-2019.