SSSO and SPSO

edited Nov 6, 2019 10:19AM in Procurement - EBS (MOSC) 9 commentsAnswered ✓

R12.1.3

We are in the process of implementing Supplier Scheduling to send PO release via EDI.

Using both the programs below to communicate the Forecast and Fire demand.

OUT: Planning Schedule (830/DELFOR)     -- Forecast

OUT: Shipping Schedule (862/DELJIT)        -- Firm.

Our question: How does oracle picks release lines to include in each schedule ( 830 or 862).

We don't see any flag in the files as Firm or Forecast type. If we have a release with 52 weeks of promisted dates. ( i.e 52 lines in the release) how does Oracle both the programs

pick these lines and places them in the two schedules.

Basically looking for the criteria.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center