Procurement - EBS (MOSC)

MOSC Banner

Can we change our approval process reducing no of approvals

edited Nov 18, 2019 7:45AM in Procurement - EBS (MOSC) 2 commentsAnswered

Can we change our approval process from: Requiistioner raises req, Budget Manager approves as per our hierarchy, thi sgoes into Autocreate. our central buyers review and create po and approve so it is sent out to suppllier.  reqs are raised through webbrowser.  we do not have AME. we want the requisitioner to raise the req, th ebudget manager to apprive and turn into a po ie cutting out the central buyer - for all req with a vlaue of £1000 or less, Any advice appreciated thanks Sally

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center