Project Reporting section doesn't update with commitment cost of Purchase Requisition,but the same c

edited Nov 12, 2019 5:06AM in Projects - EBS (MOSC) 6 commentsAnswered ✓

Hi Team,

In Project planning and control - The Reporting section is not getting updated with commitment cost which is not updated from Purchase Requisition.

We have raised Requisition for Projects and PR is approved,but the commitment cost is not updated in Reporting section after running the PRC:Update Project performance data,but the same commitment cost is updated and found in Project Status Inquiry screen.

Please find the screenshots below:

Reporting screen of Project Management

Project Status Inquiry screen

Please suggest me on this why the Reporting section in Project planning is not getting updated.

Regards

Raj

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center