P6 Trouble Calculating Earned Value and Performance % Complete
Version - P6 Professional 18.8 SQLite
OS - Windows 7, 64 Bit Operating System
Question;
Is there an issue with P6 calculating Earned Value for a schedule that has been imported from an MS Projects excel export?
Here's whats going on;
I have been able to create several project schedules that calculate Earned Value and Performance % Complete correctly. But I have this one schedule that will not show percentages, values, or calculate properly.
The only difference between this schedule and previous schedules is this schedule was an import from MS Projects as an excel document.
All settings appear to be correct.
What is not calculating properly is Estimate at Completion Cost and Estimate to Complete. The values are dumping into the Variance at Completion column where it should be in Estimate at Completion Cost and Estimate to Complete.