Durations not calculating correct number of days for the calendar

edited Dec 12, 2019 7:15PM in Primavera (MOSC) 2 commentsAnswered

I have activities assigned to an 8 hour/day calendar. A 10 hour task is showing up as a 1 day task though, as if the calendar was actually a 10 hour work day.

The calendar is a global calendar.

Anything I might be missing?