Closed Status not appearing in Projects Statuses
HI All,
we have one project and we want to close that project but in Projects Statuses 'Closed' status is not appearing. Previously when we faced this issue we identified that some Project related expenditures were interfaced through Work In Process ( EAM Work Orders ) and when we closed that EAM work orders then we were able to find the Closed status in the Projects.
But now for this similar issue even when we closed the related EAM work order the 'Closed' status is still not appearing in the Projects.
Please advise is there any process or options has to be check in order to appear Closed status in the Project Statuses.