Hello Experts, My issue is Discrete Component Pick Release is not creating Move Order for remaining
As per the issue,
I can see Move order was created for the required quantities but to complete the job required component quantities are not available in supply subinventory.
Please clarify me on this scenario
- when a move order is created for a job and transacted the material from source to supply subinventory, now in case that material was consumed by anyother job which was processed beforehand then in that case component pick release should create another move order to transact the remaining required quantities or this can't be possible.
In attached discrete job pick list report for a WIP Job, open quantity for item 2233BZDP17X28 is 189 while already supplied quantity at shop floor is 141.50. If I am trying to create a new move order for deficit quantity of 47.5 it is not creating a new move order to transact the remaining quantity.