ASCP using supplier calendar not manufacturing calendar
Hello experts,
when we checked on Planner workbench - ASCP calculating as per supplier calendar not as per manufacturing calendar for calculating dates.
in ASCP instance profile - set MSC: Use Shipping/Receiving Calendar N
so how it considering supplier calendar ??
suggested dock date = 30 Mr 2020 and sugg order date = 30-jan-2020
(procesing lead time 60 days )
supplier calendar = all work days defined .
some profiles set -
MSO: Avoid non working days for Buy/Transfer order dates = No
MSO: Enable Decision Rules = No
MSC: Buy Order Processing Lead Time Calendar = Null
MSO: Avoid non working days for Buy/Transfer order dates = Yes
MSO: Use Shift Definitions When Scheduling Lead Times= N