Calendar based PM suggesting Work Order for the same date again
Originally a PM Work Order was generated for Scheduled Completion date of Jan17-2020/ Cycle 4 per PM setup screen shot below. But the Operator completed the PM 4 days early on 13-Jan-2020. This is just one Work Order per week per PM set-up below. Now when I forecast, the PM engine is suggesting another Work Order for the same week (Jan 17th - Friday with Cycle of 5) (Please see second screen shot below). Obviously we don't need another work Order this week, we expect the Cycle 5 work Order to be scheduled on 24th Jan 2020. Is this a