ASCP Constraints plan with EDD is generating planned orders before the forecast date.

edited Jan 29, 2020 11:33PM in Value Chain Planning - EBS (MOSC) 5 commentsAnswered

ASCP Constraints plan with EDD is generating planned orders before the forecast date.

We are seeing the exception as 'Early replenishment for forecast'

Details :

My forecast dates :

27-NOV-2020 23:59:00

11-DEC-2020 23:59:00

06-NOV-2020 23:59:00

30-OCT-2020 23:59:00

27-NOV-2020 23:59:00

For this all forecast, plan generating planned orders with 14-JUL-2020 23:59:00 only.  not generating respective forecast dates.

calendar is not an issue.