ASCP Constraints plan with EDD is generating planned orders before the forecast date.
ASCP Constraints plan with EDD is generating planned orders before the forecast date.
We are seeing the exception as 'Early replenishment for forecast'
Details :
My forecast dates :
27-NOV-2020 23:59:00
11-DEC-2020 23:59:00
06-NOV-2020 23:59:00
30-OCT-2020 23:59:00
27-NOV-2020 23:59:00
For this all forecast, plan generating planned orders with 14-JUL-2020 23:59:00 only. not generating respective forecast dates.