We imported a batch of cost from Inventory, as we do every week, then distributed.  The items are normal, except for one that looks like this:

Quantity -1

Accounted Cost $2850

Denominated Cost  $0

Project Cost $0

Has anyone seen this?  Where the denominated cost is zero but the accounted cost isn't?  We tried flagging it to re-distribute and re-running the distribute process and it came out the same. 

Ideas for how to fix it?

Thanks!

J

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.