Releasing SO recommendation from ASCP does not honor override ATP flag
Hi,
when releasing a 'release' recommendation from ATP plan Schedule Ship dates on Sales Orders are updated accordingly with dates calculated by the plan, even when SO lines with Override ATP flag checked.
Does anyone know whether it is a standard functionality or is there any workaround to update only those lines, which do not have that flag checked?
Steps to reproduce:
1. Query Sales Orders with Release recommendations in ATP plan
2. Select all for release -> Release
3. Observe that SO lines with Override ATP flag checked got new Schedule Ship dated
Regards