ATP Calendar - ASCP calendar
Hi
we are using ATP (we have an atp rule linked to eg an item we sell , ATP rule based on cum total lead time)
so our items are atp enabled, are buy items and we use as well unconstrained planning.
the item does not have a sourcing rule , no ASL either.
my question is .. if the item has a lead time of 15 days ..
which calander will be taken into account if i enter a sales order ?.. and which date will be the schedule ship date ?
is ATP 24*7 and thus will schedule 2 weeks
or will it take the planning org calendar which is set to 5 on - 2 off (weekend off)