Resource Dependent Activities & Remaining Early Finish Date
I’m using resource dependent activities with dayshift and nightshift resources with calendars laid out accordingly. Occasionally, I get the “Remaining Finish Date can’t be earlier than Actual Start Date” pop up.
I’ve narrowed the conditions that cause this:
- The activities are 2 shift-10 hour-6 day calendars. The dayshift is 10 hour (0700 – 1730) & nightshift is 10 hour (1800 – 0430).
- The activities in question have uneven shifts like 2 dayshifts and 1 nightshift. The opposite hasn’t reproduced the issue, nor if the shifts are equal like 2 days and 2 nights.
- It only happens when the activity is in progress, and has one dayshift left. I.E. 30 hour duration with 10 hours remaining