Hi,

We have a issue where the user initially wanted 6 quantities of an item in a PO but due to unavailability of items the line in SO got split into two with one line with2 quantities and the other with 4 quantitites. the line with 2 quantities is closed in SO but the line with 4 quantitites is in status "Awaiting Receipt" and since these 4 quantities are not available at the moment the user wants to cancel the remaining 4 quantities in PO. Since it is an 11i instance the lines have not split at PO, at PO the