MRP does not auto-release planned orders for few items
Hi All,
We are on R12.2.7. We noticed that for few items, business has always been placing manual orders as MRP does not release planned orders.
We have followed the setups as per the below note.
How To Setup Items and MRP/ASCP Plan For Auto-Release(Doc ID 788742.1)
In Item setup, MRP/MPS Planning tab, Planning method is set to MRP Planning demand.
Planning time Fence attributes is set along with Release Time fence. We have been able to narrow down to the below scenarios.
1. We have noticed for few items in MRP workbench, Planned order is present with a past due date.