Budget Funds Check and Project Costs
Hi,
In regards to the budget funds check function when entering a project related PO for example, would it be possible to include all costs against a project?
I know the seeded build is for the budget check to only review PO / AP project related costs only, but is there any way to change this?
Our projects have multiple sources as well as numerous pre-approved batch entries, so the budget check against the project spend, to be honest is fairly useless. The PSI and Expenditure Inquiry screen hold a completely different figure.
- The Project budget is X amount E.g. 100k