Preventive Maintenance
In Preventive Maintenance when I run the forecast to see the plan I select one of the work order and implement it let say it has a suggest start date in 30/5/2020 and I run the work order in 5/5/2020 after I complete this work order I go back to run the plan again but I found that there is another work order has a suggest start date in 30/5.2020
my question is I want when I implement work order which has a specific date and complete this work order when I go back to the plan it should not appear that another work order forecasted to be created in the same date